1 Hole Cleaning & Solids Control
2 Blue cells on yellow are inputs. The well and string are the kill sheet's example: replace them with your own.
3
4 Well Geometry
5 Measured depth of the bit (TD) 12500 ft
6 True vertical depth of the bit 11800 ft
7 Casing shoe measured depth 8500 ft
8 Casing shoe true vertical depth 8200 ft
9 Casing inside diameter (9⅝" 47 lb/ft) 8.681 in
10 Bit (open hole) diameter 8.5 in
11
12 Drill String
13 Component OD (in) ID (in) Length (ft) Capacity (bbl/ft) Volume (bbl)
14 Drill pipe (length = TD less the BHA) 5 4.276 11,360 0.01776 201.8
15 Heavy-weight drill pipe 5 3 540 0.00874 4.7
16 Drill collars 6.5 2.813 600 0.00769 4.6
17 Drill string 12,500 211.1
18
19 Annulus (open hole below the shoe, casing above)
20 Section Hole ID (in) Pipe OD (in) Length (ft) Capacity (bbl/ft) Volume (bbl)
21 Drill collars × open hole 8.5 6.5 600 0.02914 17.5
22 Heavy-weight × open hole 8.5 5 540 0.04590 24.8
23 Drill pipe × open hole 8.5 5 2,860 0.04590 131.3
24 Drill collars × casing 8.681 6.5 0 0.03216 0.0
25 Heavy-weight × casing 8.681 5 0 0.04892 0.0
26 Drill pipe × casing 8.681 5 8,500 0.04892 415.8
27 Annulus 12,500 589.4
28
29 Drilling Parameters
30 Flow rate 500 gpm
31 Mud weight in (suction) 11.2 ppg
32 Highest mud weight allowed in the annulus 11.5 ppg
33 Planned rate of penetration 90 ft/hr
34 Formation porosity (fraction) 0.2 —
35
36 Cuttings Load
37 Cuttings volume per foot of hole 0.05615 bbl/ft
38 Cuttings generated at the planned ROP 5.05 bbl/hr
39 Cuttings concentration in the returns 0.70 % vol
40 Annular velocity past the drill pipe in open hole 259 ft/min
41 Annular velocity past the collars 408 ft/min
42 Maximum ROP for the annulus mud weight limit 139 ft/hr
43 ROP check OK: planned ROP within the limit
44
45 Maximum ROP against Flow Rate
46 Flow rate (gpm) Maximum ROP (ft/hr) Planned ROP (ft/hr)
47 300 83 90
48 350 97 90
49 400 111 90
50 450 125 90
51 500 139 90
52 550 153 90
53 600 167 90
54 650 181 90
55 700 195 90
56 750 209 90
57 800 223 90
58
59 Mud Solids (two-component volume balance)
60 Base fluid weight 8.34 ppg
61 Average solids specific gravity (2.6 drilled solids, 4.2 barite) 2.6 —
62 Average solids density 21.68 ppg
63 Solids content 21.4 % vol
64
65 Dilution to Bring the Mud Weight Back
66 Active system volume 800 bbl
67 Mud weight now 11.6 ppg
68 Dilution fluid weight 8.34 ppg
69 Dilution fluid to add (back to the mud weight in) 111.9 bbl
70 System volume after dilution 912 bbl
71
72 Drill Pipe Washout (marker pumped down the pipe, seen back at surface)
73 Pump output at the running efficiency 0.102 bbl/stk
74 Strokes from pumping the marker to seeing it at surface 4000 stk
75 Washout depth 6,118 ft
76 Strokes down the pipe to the washout (pipe leg) 1,065 stk
77 Washout depth from the pipe-leg strokes (check) 6,118 ft
78 Washout position check OK: the washout is in the drill pipe
79
80 Open-Hole Size from a Carbide Lag
81 Strokes from dropping the carbide to the gas peak 8300 stk
82 Lag volume 846.6 bbl
83 Open-hole annular volume, measured 219.7 bbl
84 Open-hole annular volume, in gauge 173.5 bbl
85 Excess open-hole volume 26.6 %
86 Pipe in the open hole, by OD 107.2 bbl
87 Average open-hole diameter 9.17 in
88 Hole size over bit size 1.08 —
89 Hole size check OK
Maximum ROP against flow rate 0 50 100 150 200 250 ROP (ft/hr) 300 400 500 600 700 800 Flow rate (gpm)
Maximum ROP (annulus mud weight limit) Planned ROP

Description

What the hole does to the mud, and what the mud says about the hole. For the planned ROP the sheet works out the cuttings volume per foot, the cuttings concentration in the returns, the annular velocities and the highest ROP that keeps the annulus mud weight under a limit, with that limit charted against flow rate. It gives the solids content from the mud weight and the dilution needed to bring a heavy system back to weight. Two marker calculations use the well's geometry. A drill pipe washout depth comes from the strokes until a marker is seen back at surface, and the average open-hole diameter and excess volume come from a carbide lag.

Parameters:

  • Well geometry and drill string: As on the kill sheet: bit and shoe depths, casing ID, bit size, and the OD, ID and length of each string component (ft, in)
  • Q, MW, MW limit: Flow rate (gpm), mud weight in, and the highest mud weight allowed in the annulus (ppg)
  • ROP, porosity: Planned rate of penetration (ft/hr) and formation porosity (fraction)
  • Base fluid weight, solids SG: For the solids balance (ppg, dimensionless)
  • System volume, current and dilution fluid weights: For the dilution (bbl, ppg)
  • Pump output, marker strokes, lag strokes: Output per stroke (bbl/stk), the strokes until a washout marker is seen at surface, and the strokes from dropping carbide to the gas peak (stk)

Method: Cuttings volume = Dh² / 1029.4 × (1 − φ) bbl/ft, and their concentration in the returns is the cuttings rate over mud plus cuttings, with no slip. The control-drilling limit is ROP_max = 67 (MW_max − MW_in) Q / Dh². Solids content is the two-component balance 100 (MW − MW_base) / (ρ_solids − MW_base), with ρ_solids = 8.34 × SG. Dilution = V (MW_now − MW_target) / (MW_target − MW_dilution). A washout marker travels down the pipe and back up the annulus. The return volume (strokes × output) is therefore split against pipe capacity plus annular capacity, cased first and then open hole, to give the washout depth. The strokes for the pipe leg alone are then run back through the pipe-only depth formula as a check. A carbide lag volume less the string volume and the cased annulus leaves the open-hole annulus; adding back the pipe in it by OD gives the hole volume, and from that the average diameter. The formulas are the sheet's own _PO.DE.* LAMBDAs, so it calculates with no add-in installed.

Example: Drilling 8½" hole at 90 ft/hr with 500 gpm of 11.2 ppg mud makes 0.056 bbl of cuttings per foot, 0.70% by volume in the returns. A 0.3 ppg annulus limit allows up to 139 ft/hr. With drilled solids at SG 2.6, the mud holds 21.4% solids, and 112 bbl of water brings an 800 bbl system back from 11.6 to 11.2 ppg. A marker back at surface after 4,000 strokes puts the washout at about 6,120 ft. A carbide gas peak at 8,300 strokes shows an open hole averaging 9.17", 27% over gauge.

How to use this blueprint
  1. In Excel, go to the Petroleum Office ribbon tab and click Blueprint Manager
  2. Search for Hole Cleaning & Solids Control
  3. Click on the blueprint to preview
  4. Click Insert to place it into your worksheet. Modify the input values to match your data.