Number of sacks of lead cement required for annulus

Input(s)

Lc\mathrm{L}_{\mathrm{c}}: Feet to be Cemented (ft)

Ca\mathrm{C}_{\mathrm{a}}: Annular Capacity (ft3/ft)\left(\mathrm{ft}^{3} / \mathrm{ft}\right)

E: Excess Volume (fraction)

Y: Slurry Yield of Lead Cement (ft3/\left(\mathrm{ft}^{3} /\right. stroke ))

Output(s)

Ns\mathrm{N}_{\mathrm{s}}: Sacks Required (unitless)

Formula(s)

Ns=LcCaEY\mathrm{N}_{\mathrm{s}}=\frac{\mathrm{L}_{\mathrm{c}} * \mathrm{C}_{\mathrm{a}} * \mathrm{E}}{\mathrm{Y}}

Reference(s)

Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 54.