Number of sacks of tail cement required for casing

Input(s)

\(\mathrm{L}_{\mathrm{c}}\): Distance between Float Collar and Shoe \((\mathrm{ft})\)

\(\mathrm{C}_{\mathrm{c}}\): Casing Capacity \(\left(\mathrm{ft}^{3} / \mathrm{ft}\right)\)

Y: Slurry Yield of Tail Cement \(\left(\mathrm{ft}^{3} /\right.\) stroke \()\)

Output(s)

\(\mathrm{N}_{\mathrm{s}}\): Sacks Required by Casing (unitless)

Formula(s)

\[ \mathrm{N}_{\mathrm{s}}=\frac{\mathrm{L}_{\mathrm{c}} * \mathrm{C}_{\mathrm{c}}}{\mathrm{Y}} \]

Reference(s)

Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 56.