Number of sacks of lead cement required for annulus

Input(s)

\(\mathrm{L}_{\mathrm{c}}\): Feet to be Cemented (ft)

\(\mathrm{C}_{\mathrm{a}}\): Annular Capacity \(\left(\mathrm{ft}^{3} / \mathrm{ft}\right)\)

E: Excess Volume (fraction)

Y: Slurry Yield of Lead Cement \(\left(\mathrm{ft}^{3} /\right.\) stroke \()\)

Output(s)

\(\mathrm{N}_{\mathrm{s}}\): Sacks Required (unitless)

Formula(s)

\[ \mathrm{N}_{\mathrm{s}}=\frac{\mathrm{L}_{\mathrm{c}} * \mathrm{C}_{\mathrm{a}} * \mathrm{E}}{\mathrm{Y}} \]

Reference(s)

Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 54.