Number of sacks of lead cement required for annulus
Input(s)
\(\mathrm{L}_{\mathrm{c}}\): Feet to be Cemented (ft)
\(\mathrm{C}_{\mathrm{a}}\): Annular Capacity \(\left(\mathrm{ft}^{3} / \mathrm{ft}\right)\)
E: Excess Volume (fraction)
Y: Slurry Yield of Lead Cement \(\left(\mathrm{ft}^{3} /\right.\) stroke \()\)
Output(s)
\(\mathrm{N}_{\mathrm{s}}\): Sacks Required (unitless)
Formula(s)
\[
\mathrm{N}_{\mathrm{s}}=\frac{\mathrm{L}_{\mathrm{c}} * \mathrm{C}_{\mathrm{a}} * \mathrm{E}}{\mathrm{Y}}
\]
Reference(s)
Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 54.