Plug length to set a balanced cement plug

Input(s)

Ns\mathrm{N}_{\mathrm{s}}: Number of Sacks of Cement to be Used (stroke)

AC: Annular Capacity (ft3/ft)\left(\mathrm{ft}^{3} / \mathrm{ft}\right)

Pc\mathrm{P}_{\mathrm{c}}: Pipe or Tubing Capacity (ft3/ft)\left(\mathrm{ft}^{3} / \mathrm{ft}\right)

E: Original+extra Volume Req in Percentage (fraction) Ys\mathrm{Y}_{\mathrm{s}} :Yield of Slurry (ft3/\left(\mathrm{ft}^{3} /\right. stroke ))

Output(s)

Lp\mathrm{L}_{\mathrm{p}}: Length of Plug (stroke)

Formula(s)

Lp=NsYsACE+Pc\mathrm{L}_{\mathrm{p}}=\frac{\mathrm{N}_{\mathrm{s}} * \mathrm{Y}_{\mathrm{s}}}{\mathrm{AC} * \mathrm{E}+\mathrm{P}_{\mathrm{c}}}

Reference(s)

Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 61.