Calculations for the number of feet to be cemented
Input(s)
H: Hole Size (in.)
OD: Outer Diameter (in.)
ID: Inner Diameter (in.)
Ns: Number of Sacks of Cement to be Used (sacks)
Ys: Slurry Yield (ft3/stroke)
hc: Feet of Casing (ft)
hsd: Setting Depth of Cementing Tool or Feet of Drill Pipe (ft)
DC: Drill Pipe Capacity (bbl/stroke)
E: Original+extra Volume Req in Percentage (fraction)
PO: Pump Output (bbl/stroke)
Output(s)
AC: Annular Capacity (ft3/ft)
CC∗∗: Casing Capacity (ft3/ft)
Cc: Casing Capacity (ft3)
Vs: Volume of Slurry (ft3)
ha: Height of Cement in Annulus (ft)
htc: Depth of Top of Cement in Annulus (ft3/ stroke )
Nm: Number of Barrels of Mud Required to Displace the Cement (bbl)
S: Number of Strokes Required to Displace the Cement (Strokes)
Formula(s)
AC=183.35H2−OD2CC=183.35(ID)2Cc=Ns∗YsVs=(hc−hsd)∗CCha=EAC(Vs−Cc)htc=hc−haNm=hsd∗DCS=PONmReference(s)
Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 57.