Amount of cement to be left in casing
Input(s)
\(\mathrm{L}_{\mathrm{c}}\): Casing Length \((\mathrm{ft})\)
D: Setting Depth of Cementing Tool (ft)
\(\mathrm{C}_{\mathrm{c}}\): Casing Capacity \(\left(\mathrm{ft}^{3} / \mathrm{ft}\right)\)
Output(s)
AC: Amount of Cement \(\left(\mathrm{ft}^{3}\right)\)
Formula(s)
\[
\mathrm{AC}=\left(\mathrm{L}_{\mathrm{c}}-\mathrm{D}\right) * \mathrm{C}_{\mathrm{c}}
\]
Reference(s)
Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 58.