Hydrostatic pulling

Input(s)

NS: Number of Stands Pulled (number)

Lavg: Average length per stand (ft)(\mathrm{ft})

PD: Pipe Displacement (bbl/ft)

mw: Mud Weight (ppg)

cc: Casing Capacity (bbl/ft)

pd: Pipe Disp. (bbl/ft)

Output(s)

BD: Barrel Displaced (bbl)

HP: Hydrostatic Pressure Decrease (Pulling Dry Pipe out of the Hole) (psi)

Formula(s)

BD=NSLavgPDHP=BD0.052mwccpd\begin{gathered} B D=N S * L a v g * P D \\ H P=B D * 0.052 * \frac{m w}{c c-p d} \end{gathered}

Reference(s)

Formulas and Calculations for Drilling, Production and Workover, Second Edition, Lapeyrouse, Page: 20.