Drilling ton miles - Setting casing ton miles

Input(s)

Wp\mathrm{W}_{\mathrm{p}}: Buoyed Weight of Casing (lb/ft)

Lcs\mathrm{L}_{\mathrm{cs}}: Length of One Joint of Casing (ft)

D: Depth of the Setting (ft)

Wb\mathrm{W}_{\mathrm{b}}: Weight of Travelling Block Assembly (lb)

Output(s)

Tc\mathrm{T}_{\mathrm{c}}: Setting Casing Ton Miles (ton miles)

Formula(s)

Tc=(WpD( Lcs+D)+D Wb)0.552802000\mathrm{T}_{\mathrm{c}}=\left(\mathrm{W}_{\mathrm{p}} * \mathrm{D} *\left(\mathrm{~L}_{\mathrm{cs}}+\mathrm{D}\right)+\mathrm{D} * \mathrm{~W}_{\mathrm{b}}\right) * \frac{0.5}{5280 * 2000}

Reference(s)

Lapeyrouse, N. J., 2002, Formulas and Calculations for Drilling, Production and Workover, Second Edition, Gulf Professional Publishing, Page: 47.