id: po.wb.gl.continuous-design
title: Continuous Gas-Lift Design
summary: "How much lift gas one well needs, how deep to inject it and where the unloading valves go, checked against port throughput and the nodal rate."
category: Production
requires:
  - po-addin
tags:
  - gas-lift
  - gas-lift-valve
  - valve-spacing
  - nodal-analysis
---

## Description

How much lift gas does this well need, how deep can it be injected, and where do the unloading valves go? You enter the injection pressure, lift gas, well, tubing and fluid data, the kickoff and valve data, and the reservoir pressure and productivity. You read off the injection gas rate and depth, the unloading mandrels with their test-rack settings, the operating port and its throughput, and the nodal operating point. Field units, pressures absolute; the PO add-in is needed.

**How to use it:** GL-1 and the valve port list are synthetic examples, not field measurements or vendor specifications. Enter the well, fluid and gas data on the Injection sheet and the kickoff and valve data on the Unloading sheet, replacing the defaults with measured well tests, pressure and temperature surveys, fluid properties and verified vendor specifications. Replace the synthetic productivity index on the Nodal sheet with a well test. Review Throughput and Nodal, then resolve the checks on the Summary.

**Method:** Injection calculates the gas needed to reach the target GLR, a two-pass static gas column and a Hagedorn-Brown flowing tubing profile, and interpolates the deepest point meeting the minimum valve pressure differential. Unloading places IPO mandrels on a kill-fluid line and a straight transfer line, chooses the smallest listed port with adequate Thornhill-Craver capacity, and calculates valve dome, closing and test-rack pressures. Throughput checks critical flow at the selected port. Nodal intersects a composite Darcy/Vogel oil IPR and a Beggs-Brill vertical tubing curve on finite rate grids. Summary collects the results and the checks.

**Example:** For GL-1, the 1,000 STB/d liquid rate, 300 scf/STB formation GLR and 800 scf/STB target require 500 Mscf/d of lift gas. Injection is at 7,153.76 ft, with 1,180.98 psia in the casing and 1,080.50 psia in the tubing. At spacing factor 0.2, unloading selects a 16/64 in port and six unloading valves; the first is at 2,456.23 ft with 1,130.33 psia test-rack opening. The port passes 586.08 Mscf/d. With the linked GL-1 fluid and tubing conditions and a synthetic oil productivity index of 0.34 STB/d/psi chosen to align the nodal case with the design rate, the finite-grid nodal crossing is 980.56 STB/d at 1,464.74 psia and needs 490.28 Mscf/d of lift gas. The individual gas-lift and nodal calculations, run on the same unrounded inputs, give the same numbers.

## Validity

Pressures are absolute. The injection pressure profile assumes all lift gas is present throughout the tubing; use a segmented traverse when gas enters above the node. Nodal assumes the packer depth is the node and uses total gas as free gas along the whole tubing at fixed liquid density and viscosity; compare against a measured survey and a segmented multiphase model. The nodal calculation holds total GLR constant as rate varies, so the lift gas it implies changes with rate; the nodal lift-gas check compares that demand with both the design gas rate and port capacity. The default crossing needs about 490 Mscf/d, within the 500 Mscf/d design and 586 Mscf/d port. A higher productivity may require more gas than either supplies and must be redesigned. No crossing on the displayed grid does not prove no crossing exists outside it. The design permits ten mandrels, assumes a straight transfer line and uses an illustrative port catalogue. The chart's tubing line is a straight approximation, not the calculated Hagedorn-Brown profile. The top mandrel depth balances full kickoff pressure, whereas its opening setting uses kickoff less the first drop; the first plotted kickoff balance therefore exceeds its opening setting by that drop. Review the pressure, spacing, transfer, closing and mechanical limits with the vendor.

The add-in has no dedicated valve-spacing or port-size functions; their screening equations are written in sheet cells with the valve functions. The throughput curve is omitted from this compact workbook; the valve throughput blueprint draws it. Compare correlations and validate the final design for the well.

## References

- American Petroleum Institute. *API RP 11V6, Recommended Practice for Design of Continuous Flow Gas Lift Installations Using Injection Pressure Operated Valves*.
- Brown, K.E. (1980). *The Technology of Artificial Lift Methods*, Vol. 2a. PennWell (gas lift: injection point, unloading valve spacing and valve setting).
- Takacs, G. (2005). *Gas Lift Manual*. PennWell.
- Hagedorn, A.R. and Brown, K.E. (1965). Experimental Study of Pressure Gradients Occurring During Continuous Two-Phase Flow in Small-Diameter Vertical Conduits. *JPT* 17(4), 475-484.
- Vogel, J.V. (1968). Inflow Performance Relationships for Solution-Gas Drive Wells. *JPT* 20(1), 83-92.
- Beggs, H.D. and Brill, J.P. (1973). A Study of Two-Phase Flow in Inclined Pipes. *JPT* 25(5), 607-617.

## Inputs

| Input | Unit | Default | Name |
|---|---|---|---|
| Surface operating injection pressure | psia | 1,000 | `GDI_Ps` |
| Lift-gas specific gravity | — | 0.65 | `GDI_SG` |
| Surface temperature | °F | 80 | `GDI_Ts` |
| Temperature at the packer depth | °F | 200 | `GDI_Tb` |
| Packer depth, the deepest injection point | ft | 8,000 | `GDI_Dpk` |
| Flowing wellhead pressure | psia | 120 | `GDI_Pwh` |
| Liquid rate | STB/d | 1,000 | `GDI_Ql` |
| Formation gas-liquid ratio | scf/STB | 300 | `GDI_GLRf` |
| Target total gas-liquid ratio | scf/STB | 800 | `GDI_GLRt` |
| Tubing inner diameter | in | 2.441 | `GDI_ID` |
| Tubing relative roughness | — | 0.0006 | `GDI_Rough` |
| Liquid specific gravity | — | 0.9 | `GDI_SGl` |
| Liquid viscosity | cP | 2 | `GDI_Ul` |
| Gas-liquid surface tension | dyne/cm | 30 | `GDI_IFT` |
| Minimum valve differential | psi | 100 | `GDI_dPmin` |
| Least injection depth, share of packer depth | % | 75 | `GDI_PoiMin` |
| Surface kickoff pressure | psia | 1,200 | `GDU_Pko` |
| Surface opening pressure drop per valve | psi | 25 | `GDU_Drop` |
| Kill-fluid gradient | psi/ft | 0.465 | `GDU_Gs` |
| Spacing factor | — | 0.2 | `GDU_Fs` |
| Minimum transfer differential | psi | 100 | `GDU_dPmin` |
| Discharge coefficient | — | 0.6 | `GDU_Cd` |
| Specific heat ratio | — | 1.28 | `GDU_k` |
| Bellows area | in² | 0.77 | `GDU_Ab` |
| Spring tension as pressure | psi | 0 | `GDU_St` |
| Maximum accepted spread | psi | 100 | `GDU_SpreadMax` |
| Average reservoir pressure | psia | 4,000 | `GDN_Pr` |
| Bubble-point pressure | psia | 2,620 | `GDN_Pb` |
| Oil productivity index above bubble point (synthetic, aligned to the design rate) | STB/d/psi | 0.34 | `GDN_J` |
| Water-oil ratio | — | 0.25 | `GDN_WOR` |
| Largest crossing miss against the IPR | % | 1 | `GDN_IprTol` |

## Sheets

- `Guide` — the workflow through the sheets and the scope and limitations of the screening.
- `Injection` — GL-1's lift gas, the gas properties and balance, the point of injection at the minimum valve differential, and the static gas and Hagedorn-Brown flowing pressure profiles.
- `Unloading` — the gas column and operating port, the IPO unloading valve schedule with dome, closing and test-rack pressures, and the pressure-depth design lines, charted.
- `Throughput` — Thornhill-Craver capacity and the critical-flow screen at the selected port, from the linked design conditions.
- `Nodal` — the composite IPR and the Beggs-Brill lifted tubing curve on Injection's conditions, their operating point and the lift gas it needs.
- `Summary` — the design results and every check under one verdict.
- `Test Cases` — the worked example and other cases, with expected and computed results.

One chart: the gas-lift design lines on Unloading (unloading, kickoff casing, operating casing, transfer and a linear tubing line).

## Functions used

`PO.GL.Inj.Qgi`, `PO.GL.Inj.Grad`, `PO.GL.Inj.Pd`, `PO.GL.Inj.Eff`, `PO.GL.Valve.ThornhillCraver`, `PO.GL.Valve.PPE`, `PO.GL.Valve.Pd.Required`, `PO.GL.Valve.Pvc`, `PO.GL.Valve.Spread`, `PO.GL.Valve.TRO`, `PO.VFP.HagedornBrown.Pin`, `PO.VFP.BeggsBrill.Pin`, `PO.IPR.VW.PSS.Rate.ByVogel`, `PO.PVT.Z.ByDAK`, `PO.PVT.Ppc.ByStanding`, `PO.PVT.Tpc.ByStanding`, `PO.PVT.Rho.Wat.Stn`, `PO.Spline.Linear.Interp` and `PO.Spline.Linear.Intersect`.